Resident guide · Checked November 28, 2026

Port Angeles has paused data-center permits while it writes the rules.

On September 1, 2026, the Port Angeles City Council adopted a six-month moratorium on permit applications for facilities whose principal use is digital data processing, storage, management, or transmission. Ordinary server rooms that support another use, such as a school or clinic, are excluded. The pause is temporary. The city’s FAQ states that it “does not predetermine whether data centers should or shouldn’t be allowed.” (city FAQ, questions 1–5; Resolution 12-26)

  • What it is. A temporary stop on accepting, reviewing, or approving those permit applications while the city studies impacts and drafts standards.
  • What it is not. It is not a permanent ban, and it is not a decision on any particular project.
  • No formal applications have been filed. The former McKinley Mill site has been discussed conceptually. (city FAQ, questions 4 and 11)
  • An extension is in progress. On November 17, 2026, Council authorized six more months, to end by September 1, 2027. A public hearing and formal resolution are still required and had not been scheduled as of November 28, 2026. (city FAQ, question 3; Nov. 17 Council packet)
  • Draft rules exist but are not adopted. Staff presented Municipal Code Amendment 26-0286 in October. The Planning Commission’s December 2, 2026, hearing on that draft was canceled after the extension vote. (Oct. 28 Planning Commission packet; Nov. 18 cancellation notice)
More about what the city is studying, and the mill site

The FAQ says the city is studying potential effects on the environment, local utilities, and surrounding land uses, including water and electrical demand, impacts to ratepayers, fire and emergency access, noise, and other environmental issues. Existing SEPA, critical areas, shoreline, and state and federal environmental rules already apply. (city FAQ, questions 6–8)

The former McKinley Mill site is two adjacent lots: one owned by McKinley and one owned by the city and leased to McKinley. The city is involved as a property owner, as the permit authority, and as the electric and water utility. The FAQ says the city received a letter from Candelaria Industries with conceptual ideas that did not include data-center components, and that Candelaria later presented to Council on October 20, 2026. The city has told Candelaria that, under conditions protective of other ratepayers, it can provide electricity to the site. Any sale or new lease of the city-owned lot, and any electric or water contract, would need Council approval. (city FAQ, questions 9–11)

News coverage of that presentation reported a proposal for up to nine “computing pods” in an existing mill building and a request for 9.9 megawatts of city power, along with a claim that the pods would use heat-pump-style cooling and would not need process water. Those figures and claims come from news reports of the developer’s pitch. They are not an approved project and have not been independently verified here. (Seattle Times, Nov. 16, 2026)

This is an independent resident site, not a city website. Public comment and news reports are labeled as such, separate from city findings.

Latest updates

What changed in the posted public record since this guide was last fully written.
  • November 17, 2026. City Council authorized a six-month extension of the moratorium, to end by September 1, 2027. A public hearing and formal resolution are still required and had not been scheduled as of November 28. (city moratorium FAQ, Nov. 19, 2026)
  • November 18, 2026. The Planning Commission canceled its December 2, 2026, public hearing on the draft data-center code (MCA 26-0286) because of the extension. (city cancellation notice)

The debate, without the slogans

The strongest case on each side

People who live and work here disagree. The points below are the strongest arguments in the public record, stated in plain language and tied to sources. This site does not take a position on whether data centers should be allowed.

The case for a pause and strict rules

  • The city had no data-center definition or special permit path, so it was not ready to review a large, unusual load under ordinary building rules. (Resolution 12-26; city FAQ, question 6)
  • Even a mid-size facility would be large compared with the city’s electric system. Average city load is about 28.5 aMW. A 9.9-megawatt load running around the clock would be a major addition; a 50-megawatt cap in the draft would exceed the city’s post-2028 BPA High Water Mark of 47.039 aMW. (2026 Power Resource Plan; draft 17.28.040)
  • If costs are not kept on the customer that causes them, other ratepayers can end up paying. That risk is documented in utility rate cases nationally, and the city’s own FAQ lists ratepayer impacts as a subject of study. (Harvard Electricity Law Initiative, 2025; city FAQ, question 8)
  • The city had a Stage III water shortage from August 17 to November 10, 2026, when Elwha flows were critically low. Water use depends on cooling design, but dry-year capacity is a local fact, not a hypothetical. (Nov. 10, 2026, city notice; 2025 Water Quality Report)
  • Noise, including a constant tonal hum, has been a persistent complaint in places with many data centers, and ordinary decibel limits may not capture it. Fire, fuel, and battery storage also need planning. (Loudoun County noise page; city FAQ, question 8)
  • A waterfront industrial site raises land-use and cultural-resource questions. Lower Elwha Klallam Tribe officials have been reported as opposing a data center at the mill site. That is reported comment, not a city finding. (Seattle Times, Nov. 16, 2026)

The case for allowing data centers with standards

  • The moratorium is a time-limited pause so the city can write predictable rules. It is not a decision to prohibit the use. (city FAQ, questions 2 and 5)
  • Staff have already drafted standards that would require applicant-paid infrastructure, written utility approval before a conditional-use application, closed-loop or equivalent cooling, industrial zoning for the largest facilities, and ongoing noise testing. Those drafts are not adopted, but they show a path that addresses the main concerns. (Oct. 28 Planning Commission packet; draft MCA 26-0286)
  • BPA rules charge new single loads of 10 aMW or more at a higher wholesale rate, or require non-federal power, which is designed to limit cost shifts onto other preference customers. The FAQ says the city has already told Candelaria that electricity can be provided only under conditions protective of other ratepayers. (BPA NLSL fact sheet; city FAQ, question 9)
  • Because the mill is curtailed, the city currently has unused room under its post-2028 High Water Mark. A 9.9-megawatt load might fit in that room if the mill stays down and if the load stays under the 10 aMW New Large Single Load line. (2026 Power Resource Plan)
  • Reuse of the mill site, construction work, and additions to the tax base have been raised as reasons to allow a carefully limited project. At the September 15 hearing, news coverage described speakers who urged a careful path and site reuse, including suggested standards that closely match the later draft. (Peninsula Daily News, Sept. 18, 2026)
  • SEPA, critical areas, shoreline, and other environmental rules already apply. A rural-county state sales-tax exemption exists, but it requires a minimum building size and family-wage jobs, and the refurbishment-certificate path closed on July 1, 2026. (city FAQ, question 6; RCW 82.08.986)

Checked against the public record

Concerns and what the evidence shows

Each item starts with a concern raised in official city materials or, where noted, in news coverage or public comment. The verdict is about what the cited record shows, not about whether you should support or oppose a project. Open a topic for the details.

8 topics, closed until you open one
No local definition or standards Supported
The concern
The city did not have a definition of “data center” or a specific permit path, so staff would have had to treat an application like an ordinary building permit.
What the evidence shows
Resolution 12-26 and the September 1 staff memo state that the municipal code has not defined data centers or set review rules. The November 19 FAQ repeats that the code “does not specifically define data centers as a land use.” That is a documented gap and a stated reason for a temporary pause. It does not, by itself, establish any particular impact from a future project.
Verdict
Supported
Electrical demand compared with the city utility Supported as to scale; service depends on the project
The concern
A data center could draw far more electricity than other commercial uses and could strain a small municipal utility.
What the evidence shows
The city’s adopted 2026 Electric Utility Power Resource Plan shows average load of 28.48 average megawatts (aMW) in 2025, nearly all of it Bonneville Power Administration (BPA) Tier 1 power, with no Tier 2 purchases. The plan assumes the McKinley mill stays curtailed and that the city’s post-2028 BPA Contract High Water Mark is 47.039 aMW. A facility of about 9.9 megawatts running around the clock would add on the order of one-third to today’s average city load and could still fit under that High Water Mark if the mill stays down. The draft code’s 50-megawatt cap would not; it would exceed the High Water Mark and require Tier 2 or other power. Under the Northwest Power Act, a new load that grows by 10 aMW or more at a single facility in a 12-month period is a New Large Single Load and is served at BPA’s higher New Resources rate, or with non-federal power, not low-cost preference power. A 9.9-megawatt request, reported in news coverage as the developer’s figure and not confirmed in a permit, sits just under that 10 aMW line. The FAQ says the city has told Candelaria Industries that it can provide electricity “under certain conditions protective of other rate payers.” Whether a specific project can be served depends on its size and on any upgrades the applicant pays for. The 2026 plan publishes average load, not a peak-load figure.
Verdict
Supported that a mid-size or large facility would be large relative to the city’s system. Whether a given project can be served depends on its size and on paid upgrades.
Effects on other ratepayers’ bills Partly supported — a real risk, not a given
The concern
Existing electric customers could see higher bills if the costs of serving a large new load are spread across the utility.
What the evidence shows
The city’s FAQ lists “potential impacts to ratepayers” as a subject of study. The October 28 Planning Commission staff report and the draft code would require applicants to fund attributable infrastructure and power costs and to obtain written utility approval before applying for a conditional-use permit. Those drafts are not adopted. A March 2025 paper from the Harvard Electricity Law Initiative, reviewing nearly 50 rate cases, found that ordinary rate design and special contracts can shift generation and transmission costs from large data-center loads onto other customers. That paper is about utility rate design in general, not a Port Angeles study. BPA’s New Large Single Load rule is meant to limit that shift at the wholesale level for loads of 10 aMW or more. Smaller loads can still use remaining Tier 1 headroom, which exists here largely because the mill is curtailed. No project-specific Port Angeles cost-of-service study of a data center appears in the Council or committee packets reviewed for this guide.
Verdict
Partly supported. The risk is documented in utility rate design generally and is a stated local concern. It is not inevitable, and the city has not published a project-specific rate study.
Water demand and the Elwha supply Depends on cooling technology
The concern
Cooling a data center could use large amounts of water, in a city that recently had a shortage.
What the evidence shows
The city’s 2025 Water Quality Report says the source is a Ranney well by the Elwha River, the treatment plant’s net capacity is 10.2 million gallons a day, and typical production is 2 to 4 million gallons a day. A Stage III water shortage was declared on August 17, 2026, because Elwha flows were critically low, reaching about 198 cubic feet per second on October 24, and was lifted on November 10, 2026. That shortage is a documented fact. Water use by a data center depends mainly on cooling technology: evaporative or once-through systems can use large amounts of water; closed-loop, air, or heat-pump systems use little on-site water after the initial fill, though they usually use more electricity. The draft code would require closed-loop or equivalent cooling, prohibit once-through cooling, and let the city cap daily and annual use. News coverage of Candelaria’s October 20 presentation reported a claim that the computing pods would use heat-pump-style cooling and would not need process water. That is a developer claim, not a reviewed permit finding, and it has not been independently verified here. Even a low-water design would still need the city to confirm treatment, storage, and distribution capacity in dry years. A general claim that every data center would use unsustainable amounts of water is not supported.
Verdict
Depends on the project. The recent shortage is supported. Water use is not inherently high for every cooling design.
Noise from cooling equipment and generators Partly supported — documented elsewhere; untested here
The concern
Constant cooling and backup-generator testing could produce noise that is hard for neighbors to live with, including a tonal hum that ordinary decibel limits may miss.
What the evidence shows
The FAQ lists noise compliance as a subject of study. No data center is operating in Port Angeles, so there is no local measurement. Loudoun County, Virginia, which has nearly 200 operating data centers, says noise complaints are among the most persistent issues brought to the county, especially tonal “hum” and low-frequency sound that standard A-weighted (dBA) limits often miss. Loudoun requires pre- and post-construction noise studies and a 55 dBA residential limit, and it is still rewriting its standards. Port Angeles’s draft code would require a professional assessment that includes low-frequency and tonal noise, testing after opening, quarterly monitoring, and weekday-only generator tests, except in an emergency. Those draft rules are not adopted. Impacts would depend on design, location, and how noise is measured and enforced.
Verdict
Partly supported as a documented issue at other data-center sites. Unproven in Port Angeles because no facility exists here.
Fire and emergency access Partly supported as a planning issue
The concern
Backup generators, fuel storage, and batteries could create fire or emergency-access problems.
What the evidence shows
Backup generators, fuel, and battery energy storage are standard at many data centers and are already covered by fire, building, and air-quality rules. The FAQ lists fire and emergency access as a subject of study. The draft code would let the Fire Marshal require an emergency-response plan covering fire suppression, battery thermal runaway, hazardous materials, shutdown, and access, and would not automatically allow generators to run for market power. Those drafts are not adopted. No Port Angeles-specific fire analysis of a data-center proposal appears in the packets reviewed for this guide. The concern is a legitimate planning issue; it has not been shown to be unmanageable under existing and proposed rules.
Verdict
Partly supported as a legitimate planning issue. Not shown to be unmanageable.
Land use, the waterfront mill site, and cultural resources Depends on the site and the project
The concern
A data center on the former McKinley Mill site could affect the waterfront, nearby uses, and cultural resources.
What the evidence shows
Resolution 12-26 identifies potential impacts to surrounding land uses. The FAQ says existing State Environmental Policy Act (SEPA), critical areas, shoreline, and other state and federal environmental rules already apply, and that the city is writing data-center-specific standards anyway. The mill site is two adjacent lots, one owned by McKinley and one owned by the city and leased to McKinley. The FAQ says the lessee is obligated to return the city lot in as good order as when the 1967 lease was signed, and that no formal permit applications have been filed. Any sale or new lease of the city-owned lot, and any electric or water contract, would need City Council approval. News coverage of comments by Lower Elwha Klallam Tribe officials, including a statement that tribal leaders told the prospective buyer they would not support a data center at the site, is reported in the Seattle Times. Those are reported comments, not city findings. They would be part of the public record if a project is proposed. Permits can require tribal consultation under state and federal law, as the same article notes.
Verdict
Depends on the site and the project. Existing environmental rules already apply. Tribal and cultural concerns are reported, not city findings.
Jobs, taxes, and the state sales-tax exemption Depends on the project
The concern
A data center might bring few permanent jobs relative to its power use, or might receive tax breaks that reduce the local return. Others argue it could support reuse of the mill site, construction work, and the tax base.
What the evidence shows
These points have been raised in public comment and news coverage, not as city findings. At the September 15, 2026, hearing, the Peninsula Daily News reported a speaker citing job losses after the mill closed and another asking the city not to provide tax incentives, to cap power at 50 megawatts, to require closed-loop cooling, and to limit sites to industrial zones. State law (RCW 82.08.986) can exempt sales and use tax on eligible server equipment and power infrastructure at an “eligible computer data center” in a rural county, with at least 20,000 square feet used for working servers, and a net gain of 35 family-wage jobs or, if lower, three such jobs per 20,000 square feet. New exemption certificates cannot be issued after July 1, 2036. The path for certificates based on refurbishment closed on July 1, 2026, so a project that is mainly a remodel of an existing building may not qualify; new construction in a rural county still can. Clallam County meets the rural-county definition in RCW 82.14.370: the Washington Office of Financial Management’s April 1, 2026, estimate is 79,250 people on 1,738.7 square miles, or 45.58 people per square mile, under the 100-person threshold. Whether any local project would qualify is not known. The city has not published a fiscal study of a data center, and Council has not decided whether to grant or withhold any local subsidy.
Verdict
Depends on the project. Clallam County qualifies as a rural county for the state exemption, but a given project may or may not meet the other tests.

Key studies and comparable policies

National and regional research, plus how other Washington utilities have handled large computing loads.

These are starting points, not a verdict on any Port Angeles proposal. Local numbers, where they exist, are in the concerns section above.

The city’s October 28 staff report compared other Washington approaches, including Seattle City Light large-load rates and developer-funded infrastructure, Chelan County PUD data-center rate schedules, and zoning or noise rules in Quincy, Wenatchee, East Wenatchee, Warden, Moses Lake, and Pierce County. The September 1 staff memo also noted moratoria in Seattle, Burien, and Tukwila on applications over 20 MVA. (Oct. 28 Planning Commission packet; Sept. 1 staff memo)

Open questions

What the official record, as of November 28, 2026, does not yet answer.
  • The formal public hearing on the extension has not been scheduled, and no new findings of fact for the extension are on the December 1, 2026, Council agenda. (Meetings and Agendas; Nov. 17 staff memo)
  • There is still no formal permit application, so there is no project-specific SEPA analysis, utility service agreement, water-conservation plan, or noise or fire study.
  • The official record does not state how many megawatts the city has offered to supply, or on what rate terms, only that service is possible “under certain conditions protective of other rate payers.” (city FAQ, question 9)
  • The 2026 resource plan does not include a public peak-load figure or a modeled 9.9-megawatt or 50-megawatt data-center scenario. (2026 Power Resource Plan)
  • It is not clear from the public packets whether a 9.9-megawatt project would later be treated as a New Large Single Load if it expanded, or whether multiple “pods” would be counted as one facility.
  • It is not clear whether a project in an existing mill building could claim the state sales-tax exemption now that the refurbishment-certificate path has closed. (RCW 82.08.986)
  • Council has not decided whether data centers will be allowed, at what size, in which zones, or with what local financial incentives.
  • The Planning Commission has not made a recommendation on the draft code. As of the October 28 staff report, the draft had not had legal review. (Oct. 28 staff report)
  • The Washington Data Center Workgroup’s final report, and any 2027 state legislation, are still outstanding. (Department of Revenue workgroup page)

Have your say

How to comment

The public hearing on the extension has not been scheduled. The city says it will announce that hearing and will take comment on the draft regulations through the Planning Commission and the Utility Advisory Committee before Council takes final action. Watch the city’s Meetings and Agendas page and the moratorium FAQ for the notice. You do not have to wait for the hearing to write. (city FAQ, questions 13–14)

  • City Council. Email all seven members at council@cityofpa.us, or mail City of Port Angeles City Council, 321 East 5th Street, Port Angeles, WA 98362. Written comments to that address are not read aloud. You may also speak during the public-comment period at a regular meeting (up to three minutes). Regular meetings are at 6:00 p.m. PT on the first and third Tuesday of the month, in Council Chambers and online. Check that meeting’s agenda for Webex details. (City Council page; Watch Live Meetings)
  • Planning Commission and draft code. Email the Planning Division at ced@cityofpa.us, or write to Community and Economic Development, 321 East 5th Street, Port Angeles, WA 98362, phone 360-417-4750. The Commission’s next regular meeting is Wednesday, January 27, 2027, at 6:00 p.m. PT, unless the city later notices a special meeting. (Planning Commission page; Nov. 18 cancellation notice)
  • Utility Advisory Committee. The committee advises Council on utility policy. It meets at 3:00 p.m. PT on the second Tuesday of the month, unless canceled. Each agenda states how to give public comment and where to send written comments for that meeting. (Utility Advisory Committee page; Meetings and Agendas)
  • Speak online or in person. Meetings are hybrid. For virtual comment, use the Webex “raise hand” feature or press *3 if you called in. State your name and whether you live in the city. Instructions are on the city’s live-meetings page and on each agenda. (Watch Live Meetings)
  • Questions about process. City Clerk Kari Martinez-Bailey, cityclerk@cityofpa.us or kmbailey@cityofpa.us, 360-417-4634. (City Council page)

Port Angeles City Council and Planning Commission meetings also appear on this site’s meetings calendar when they are in the city’s public feeds. The letter form below is a formatting helper. It does not take a position for you. Nothing you type is stored or sent until you copy it or open your own email app.

1. About you (all optional)

A town is enough. Do not enter a house number or parcel number. Nothing here is stored.

2. Topics you want the city to address (optional)

Topics to mention in your letter

3. In your own words

Your comment

Subject
Comment on the Port Angeles data center moratorium
Your letter will appear here.
Open in Email App

If a blank message opens, use Copy Email Text and paste it in. Some phone email apps limit long links.

Dates and timeline

Official actions from August 2026 through the next scheduled Planning Commission meeting.
  1. August 18, 2026. Council agreed to place a possible data-center moratorium on a later agenda, after a request from Councilmember Suggs. (Sept. 15 packet, recounting the Aug. 18 action)
  2. September 1, 2026. Council adopted Resolution 12-26, 6–0 (Councilmember Miller excused), effective immediately, for six months. (Resolution 12-26 and Sept. 1 minutes)
  3. September 15, 2026. Council held the public hearing required within 60 days. (Sept. 15 hearing staff report; Peninsula Daily News, Sept. 18, 2026)
  4. October 20, 2026. Candelaria Industries presented to Council. (city FAQ, question 11)
  5. October 28, 2026. Planning Commission received a first look at draft MCA 26-0286. (Oct. 28 packet; Peninsula Daily News, Oct. 30, 2026)
  6. November 10, 2026. The Utility Advisory Committee voted 4–1 to recommend a six-month extension. (Nov. 17 staff memo)
  7. November 17, 2026. Council voted 5–0 (Mayor Dexter and Councilmember Suggs absent) to authorize a six-month extension, to end by September 1, 2027. Formal steps, including a public hearing, remain. (city FAQ; Nov. 17 packet; Peninsula Daily News, Nov. 18, 2026)
  8. November 18, 2026. The Planning Commission canceled its December 2 hearing on the draft code. The next regular Commission meeting is January 27, 2027, at 6:00 p.m. PT. (cancellation notice)
  9. November 19, 2026. The city published a moratorium FAQ. (city FAQ)
  10. Still ahead. The extension hearing date has not been set. Watch Meetings and Agendas and this site’s meetings calendar.

Sources

City, state, and research documents behind every claim on this page. Checked November 28, 2026.

Every factual claim on this page comes from a public document linked here. News reports and public comments are labeled as such. If the city posts a newer agenda, ordinance, or FAQ, the city’s version controls.